← Projekte CS-2026-SA-JED-0001 REFERENCE / LOCKED
Jeddah Reference Project
Jeddah, Saudi Arabia
10000.0 m² · 4000.0 Paneele · 50000 m³/h CALCULATED
Climate / EPW
Jeddah.epw
Jeddah-Abdulaziz.Intl.AP, SAU · 8760 h
SHA-256 bb1afd72ea9a42f2…
ARE_AZ_Abu.Dhabi-Bateen.Exec.AP.412160_TMYx.2011-2025.epw
Abu.Dhabi-Bateen.Exec.AP, ARE · 8760 h
SHA-256 1631528ee2411ae6…
HUN_NGP_Szolnok.AB.128600_TMYx.2011-2025.epw
Szolnok.AB, HUN · 8760 h
SHA-256 1664a3cfe2204bf5…
ARE_DU_Dubai.Minhad.Ab.412164_TMYx.2011-2025.epw
Dubai.Minhad.Ab, ARE · 8760 h
SHA-256 95fe708d2331b0e9…
TWN_NOR_Hsinchu.AP.467560_TMYx.2011-2025.epw
Hsinchu.AP, TWN · 8760 h
SHA-256 a1dd22c483401272…
ESP_IB_Palma.de.Mallorca.AP-Son.San.Juan.AFB.083060_TMYx.2011-2025.epw
Palma.de.Mallorca.AP-Son.San.Juan.AFB, ESP · 8760 h
SHA-256 7533d562dfae5564…
NLD_NB_Eindhoven.AP.063700_TMYx.2011-2025.epw
Eindhoven.AP, NLD · 8760 h
SHA-256 5a4dd2b22593d6bb…
Neues Szenario
Operating = ASSUMED
Scenarios
| ID | EPW | AFD | Tin | nx | Status | |
|---|---|---|---|---|---|---|
| JEDDAH-0471-NX16 | Jeddah.epw | 5.0 | 16.0 | 16 | REFERENCE · LEGACY 🔒 |
Simulation Results
CS-ENGINE-0.4.7.1 · forced-flow baseline · mixed convection NOT APPLIED · physical yield TO BE VALIDATED.
Energy & PV Baseline
Energy result: RUN-20261121225027 · Scenario: JEDDAH-0471-NX16
| Metric | Value | Evidence |
|---|---|---|
| Cooling electricity | 661.93 MWh/a | CALCULATED · COP ASSUMED |
| Fan electricity | 0.00 MWh/a | MODELLED / CALCULATED |
| Fan Δp | {} Pa | - |
| Fan electric power | {} W | MODELLED |
| Gap air velocity | {} m/s | MODELLED |
| Fan Reynolds number | {} | MODELLED |
| Flow regime | {} | CALCULATED CLASSIFICATION |
| f laminar (64/Re) | {} | CALCULATED COMPARATOR |
| f Swamee-Jain | {} | MODELLED COMPARATOR |
| f Churchill | {} | MODELLED · TRANSITION CAPABLE |
| Δp gap – Swamee-Jain | {} Pa | MODELLED COMPARATOR |
| Δp gap – Churchill | {} Pa | MODELLED COMPARATOR |
| Local loss ΣK | {} | ASSUMED |
| Δp local | {} Pa | CALCULATED FROM ASSUMED K |
| Δp system | {} Pa | MODELLED |
| Fan efficiency η | {} | ASSUMED |
| Fan model | MANUAL_SPECIFIC_LOAD | MODELLED |
| Pump electricity | 0.00 MWh/a | MODELLED / CALCULATED |
| Pump total flow | {} L/min | CALCULATED |
| Pump peak flow | {} L/min | MODELLED |
| Coolant design ΔT | {} K | ASSUMED |
| Hydraulic zones | {} | CALCULATED FROM PANELS / ZONE |
| Panels / hydraulic zone | {} | ASSUMED / TO BE ENGINEERED |
| Zone pipe | {} mm · {} m | ASSUMED |
| Zone pipe velocity | {} m/s | MODELLED |
| Zone pipe Δp | {} Pa | MODELLED |
| Main hydraulic loops | {} | ASSUMED ARCHITECTURE |
| Main pipe | {} mm · {} m | ASSUMED |
| Main pipe velocity | {} m/s | MODELLED |
| Main pipe Δp | {} Pa | MODELLED |
| Channel flow | {} L/min | CALCULATED |
| Coolant velocity | {} m/s | MODELLED |
| Coolant Reynolds | {} | MODELLED |
| Channel Δp | {} Pa | MODELLED · RECTANGULAR LAMINAR |
| Pump system Δp | {} Pa | MODELLED |
| Pump electric power | {} W | MODELLED |
| Pump peak electric power | {} W | MODELLED |
| Optimizer criterion | {} | MODELLED DESIGN SEARCH |
| Optimizer balanced loops | {} | MODELLED |
| Optimizer balanced main Ø | {} mm | MODELLED |
| Optimizer balanced pump energy | {} MWh/a | MODELLED COMPARATIVE |
| Optimizer balanced peak velocity | {} m/s | MODELLED |
| Optimizer feasible variants | {} / {} | CALCULATED |
| Energy-min variant | {} loops · Ø {} mm · {} MWh/a | MODELLED COMPARATIVE |
| Infrastructure-min variant | {} loops · Ø {} mm · proxy {} m³ | MODELLED PROXY |
| Pareto variants | 0 | CALCULATED |
| Total CS electricity | 661.93 MWh/a | CALCULATED |
| EPW GHI | 2225.62 kWh/m²a | SOURCE_DATA |
| PV area | 7000.00 m² | CALCULATED FROM SURFACES |
| Installed PV | 1400.00 kWp | CALCULATED |
| PV generation | 2616.06 MWh/a | MODELLED |
| PV reference plane | ORIENTED_POA_ISOTROPIC_SKY | MODELLED |
| PV transposition | ISOTROPIC_SKY | MODELLED |
| Annual energy balance | 1954.13 MWh/a | CALCULATED |
| Hourly CS load | 661.93 MWh/a | CALCULATED FROM HOURLY MODEL |
| PV direct use | 335.13 MWh/a | CALCULATED · NO STORAGE |
| PV surplus | 2280.93 MWh/a | CALCULATED · NO STORAGE |
| Grid import | 326.80 MWh/a | CALCULATED · NO STORAGE |
| PV self-consumption | 0.128 | CALCULATED · DIRECT PV / PV |
| CS self-sufficiency | 0.506 | CALCULATED · DIRECT PV / CS LOAD |
| Peak CS load | 198.39 kW | MODELLED / CALCULATED |
| Peak PV | 1192.25 kW | MODELLED |
| Peak grid import | 170.41 kW | CALCULATED |
Hourly Energy Diagnostics
| Diagnostic | Value | Evidence |
|---|---|---|
| CS active hours | 8750 | CALCULATED |
| Hours with PV surplus | 4014 | CALCULATED |
| Hours with grid import | 4740 | CALCULATED |
| Active CS hours fully supplied by PV | 4010 | CALCULATED · NO STORAGE |
| Maximum PV surplus | 1134.08 kW | CALCULATED |
| Maximum deficit / grid import | 170.41 kW | CALCULATED |
Monthly Energy Matching
| Month | CS MWh | PV MWh | Direct MWh | Surplus MWh | Grid MWh | CS self-suff. | PV self-cons. |
|---|---|---|---|---|---|---|---|
| Jan | 27.52 | 160.34 | 13.25 | 147.09 | 14.27 | 48.2% | 8.3% |
| Feb | 25.37 | 168.55 | 12.44 | 156.12 | 12.93 | 49.0% | 7.4% |
| Mar | 35.42 | 232.00 | 19.18 | 212.82 | 16.24 | 54.1% | 8.3% |
| Apr | 44.62 | 249.78 | 24.76 | 225.02 | 19.86 | 55.5% | 9.9% |
| May | 64.78 | 273.33 | 34.06 | 239.26 | 30.72 | 52.6% | 12.5% |
| Jun | 70.13 | 259.75 | 39.01 | 220.74 | 31.12 | 55.6% | 15.0% |
| Jul | 75.99 | 260.08 | 40.88 | 219.19 | 35.10 | 53.8% | 15.7% |
| Aug | 86.86 | 247.78 | 44.10 | 203.69 | 42.76 | 50.8% | 17.8% |
| Sep | 79.64 | 224.72 | 37.41 | 187.31 | 42.22 | 47.0% | 16.6% |
| Oct | 71.76 | 210.03 | 33.89 | 176.14 | 37.87 | 47.2% | 16.1% |
| Nov | 48.31 | 171.61 | 21.54 | 150.07 | 26.77 | 44.6% | 12.6% |
| Dec | 31.53 | 158.08 | 14.60 | 143.49 | 16.94 | 46.3% | 9.2% |
Energy Matching by EPW Hour
| EPW hour | CS MWh/a-bin | PV MWh/a-bin | Direct | Surplus | Grid |
|---|---|---|---|---|---|
| 01 | 26.06 | 0.00 | 0.00 | 0.00 | 26.06 |
| 02 | 25.75 | 0.00 | 0.00 | 0.00 | 25.75 |
| 03 | 25.41 | 0.00 | 0.00 | 0.00 | 25.41 |
| 04 | 24.89 | 0.00 | 0.00 | 0.00 | 24.89 |
| 05 | 24.75 | 0.00 | 0.00 | 0.00 | 24.75 |
| 06 | 24.55 | 0.81 | 0.81 | 0.00 | 23.74 |
| 07 | 24.37 | 21.75 | 16.03 | 5.72 | 8.34 |
| 08 | 24.92 | 85.38 | 24.90 | 60.48 | 0.02 |
| 09 | 26.29 | 173.38 | 26.29 | 147.10 | 0.00 |
| 10 | 28.05 | 256.58 | 28.05 | 228.54 | 0.00 |
| 11 | 29.79 | 321.84 | 29.79 | 292.05 | 0.00 |
| 12 | 29.78 | 360.70 | 29.78 | 330.92 | 0.00 |
| 13 | 30.38 | 368.92 | 30.38 | 338.54 | 0.00 |
| 14 | 30.55 | 345.81 | 30.55 | 315.26 | 0.00 |
| 15 | 30.12 | 293.23 | 30.12 | 263.11 | 0.00 |
| 16 | 29.33 | 215.92 | 29.33 | 186.58 | 0.00 |
| 17 | 29.24 | 122.85 | 29.23 | 93.63 | 0.02 |
| 18 | 29.17 | 41.72 | 23.15 | 18.57 | 6.01 |
| 19 | 28.90 | 6.51 | 6.05 | 0.46 | 22.85 |
| 20 | 28.74 | 0.66 | 0.66 | 0.00 | 28.08 |
| 21 | 28.67 | 0.00 | 0.00 | 0.00 | 28.67 |
| 22 | 27.91 | 0.00 | 0.00 | 0.00 | 27.91 |
| 23 | 27.33 | 0.00 | 0.00 | 0.00 | 27.33 |
| 24 | 26.98 | 0.00 | 0.00 | 0.00 | 26.98 |
EPW hours are end-of-hour labels (1–24). Diagnostics aggregate the same hourly arrays used by v0.9.0; no storage or load shifting is applied.
v1.0 Energy Architecture
GRID-COUPLED PV WITHOUT STORAGE. PV is used directly when coincident with CS demand. Surplus is treated as grid export potential; deficits are grid import. Battery, chilled-water, PCM and ice storage are not part of the v1.0 product baseline. The storage investigation is preserved as a research branch.
v1.3 Advanced Grid Economics
| Metric | Value | Evidence |
|---|---|---|
| Grid import | 326.80 MWh/a | CALCULATED FROM HOURLY MATCHING |
| Grid export | 2280.93 MWh/a | CALCULATED FROM HOURLY MATCHING |
| Curtailed export | 0.00 MWh/a | CALCULATED |
| Import cost | € 32679.79/a | CALCULATED · TARIFF PROJECT INPUT |
| Export revenue | € 34213.97/a | CALCULATED · TARIFF PROJECT INPUT |
| Fixed grid cost | € 0.00/a | PROJECT INPUT / ASSUMED |
| Peak grid import | 170.41 kW | CALCULATED FROM 8760 HOURS |
| Demand charge | € 0.00/a | CALCULATED · PROJECT INPUT |
| Weighted import price | € 100.00/MWh | CALCULATED |
| Weighted export price | € 15.00/MWh | CALCULATED |
| Net grid energy cost | € -1534.19/a | CALCULATED |
| Break-even export price | € 14.33/MWh | CALCULATED DIAGNOSTIC |
v1.3 uses the actual 8760 hourly import/surplus arrays. Off-peak/peak tariffs, demand charge and export limit are PROJECT INPUT / ASSUMED. Economic post-processing only: no storage, no load shifting and no change to the physical baseline. Taxes and detailed grid fees are not yet modelled.
v1.4 Project Economics / Energy Cash Flow
| Metric | Value | Evidence / boundary |
|---|---|---|
| Direct PV use | 335.13 MWh/a | CALCULATED FROM 8760 HOURS |
| Direct PV avoided-purchase value | € 33513.14/a | CALCULATED · COINCIDENT IMPORT TARIFF |
| Export revenue | € 34213.97/a | FROM v1.3 GRID ECONOMICS |
| Gross energy value | € 67727.11/a | CALCULATED |
| Annual project OPEX | € 0.00/a | PROJECT INPUT / ASSUMED |
| Year-1 net project cash flow | € 67727.11 | CALCULATED · ENERGY-ONLY |
| Project CAPEX | € 0.00 | PROJECT INPUT / ASSUMED |
| NPV | € 664954.78 | CALCULATED · ENERGY-ONLY |
| Simple payback | - years | CALCULATED DIAGNOSTIC |
| Discounted payback | - years | CALCULATED DIAGNOSTIC |
Energy-only project cash flow. Direct PV is valued at the coincident import tariff; export at v1.3 tariff. Demand/fixed grid charges are reported but not claimed as avoided investment benefits because a no-PV counterfactual peak/grid contract is not yet modelled. Water value, cooling-service value, taxes, financing and full ClimaStrat CAPEX allocation are excluded.
PV Surface Diagnostics
| Surface | Area | Tilt | Azimuth | Annual POA | Installed | Generation | Specific yield kWh/kWp·a | Share |
|---|---|---|---|---|---|---|---|---|
| ROOF_HORIZONTAL | 7000.00 m² | 0.0° | 180.0° | 2198.37 kWh/m²a | 1400.00 kWp | 2616.06 MWh/a | 1868.6 | 100.0% |
Azimuth: N=0°, E=90°, S=180°, W=270°. EPW GHI/DNI/DHI = SOURCE_DATA; POA and generation = MODELLED; module efficiency, PR and albedo = ASSUMED.